March – Week 4 – Brick selection almost there, and 4″ siding installed
Now that we have the foundation drain installed and the block up and ready to support the brick, the pressure is on to make a brick selection.
March – Week 3 – Foundation drain installed and Siding begins!
We did have a little rain, but resolved that we were still going to be OK to install the foundation drain without scouring the footings again.
March – Weeks 1 & 2 – Basement ceiling demo, Foundation wall dampproofing
After a couple of weeks of planning and reviewing our budget and expenses, we are back in the swing again.