We were excited to see the tile guys out and finally getting started with all the selections that we have made.
Blog
August – Week 4 – Interior trim, more drain pipes & the last Crepe Myrtle
We’re trying to stay ahead of the subcontractors with our selections, but it is tough.
August – Week 3 – New driveway, linoleum, cabinets & more digging in the dirt
We concentrated on getting all the underground pipes in around the Garages last Saturday because . . .
August – Week 2 – Driveway demolition, trenching and hauling dirt
What a week for the outside work – hot and humid!
August – Week 1 – Scheduling, removing crossties, chimney flashing, tile board, and scripture writing
As we get closer to the end, we thought it would be a good idea to try to put together a schedule . . .
July – Week 4 – Making selections, Air Conditioning!, small stuff, & digging in the dirt again
We’re starting to see a glimpse of the light at the end of the tunnel – but there’s still a lot to do before we get there!
July – Week 3 – Compressors set, chimney capped, silt fence added, & driveway cleaned-up
As I mentioned last week, the Gernatts were all on vacation this week, so not much hands-on work, but a couple of subs were there during the week.
July – Week 2 – Front Porch work – just in time for a deluge
Looks like the momentum is going to take a break.
July – Week 1 – interior trim, stairs, eyebrow roof, and more grading
Another exciting week with the trim guys busy installing all that trim that we designed for the house.
June – Week 5 – hardwoods, doors, trim, columns, metal roof, and grading – all make for a full week!
As we anticipated, it was some kind of busy at 637 Polk this week!